Final Middle Road Paving

The final paving on Middle Road will occur as soon as we have 3 consecutive days without rain. We will post as soon as the paving... more ››

Route 9 Update

The Route 9 Road Closure will end this Friday, May 3rd. Beginning next week, the road will be open to one lane of traffic. Please expect... more ››

Two Week Route 9 Road Closure

Beginning on Monday, April 22nd and concluding on Friday, May 3rd, Route 9 will be closed to through traffic from the Tuttle/Blanchard Road... more ››

Middle Road Update - November 13th

The final paving of Middle Road will occur in the Spring of 2019. In the next few weeks, crews will be winterizing driveways. This will be... more ››

Route 9 Update - November 13th

Due to consistent bad weather and colder temperatures, the work on Route 9 will be completed in the Spring of 2019.

Route 9 Paving - Tuesday, October 16th

Crews will begin paving Route 9 (Main Street) on Tuesday, October 16th. Expect long delays and seek alternate routes, if possible. 

Main Street Paving

Paving will begin next week on the lower portion of Main Street, between Wyman Way and Turkey Lane.

Tuttle Road Paving

In the next two weeks, the small portion of Tuttle Road that was not paved (between the railroad tracks and Twin Brook) will be completed.

Middle Road Paving

Paving will begin next week on Middle Road. The work will take approximately 4-5 days to complete.

Route 9 Update

A. H. Grover, Inc.

Recycling Shredded Paper

Middle Road Project Summary

 

Tuttle Road Project Summary

Skillin Road Update

Work on Skillin Road will begin next week! The Town will be replacing the roadway between Pond Shore Drive and approximately 500 feet west... more ››

Route 9 Update

Work on Route 9 has been delayed until mid-September. When the work begins, Main Street from just south of Wyman Way to the Tuttle Road... more ››

w

Middle Road Project - August 2nd Update

On Thursday, July 26th Storey Brothers completed the excavation for full depth road reconstruction at the Falmouth Town Line.  The crew... more ››

a

Tuttle Road Project - August 2nd Update

On Thursday, July 26th Grover hauled and placed material for fill area of road reconstruction project to prepare for new culvert... more ››

a

Tuttle Road Project - August 9th Update

On Thursday, August 02 A. H.

r

Mill Road Closure (August 13th-17th)

The box culvert located on Mill Road, near the intersection of Blanchard Road, is scheduled to be replaced the week of August 13th-17th. ... more ››

m

Middle Road Project - July 26th Update

On Thursday, July 19th Storey Brothers began removing pavement.  On Friday, July 20th they began box cut for road reconstruction at STA 14+... more ››