Middle Road Project - July 26th Update

m

On Thursday, July 19th Storey Brothers began removing pavement.  On Friday, July 20th they began box cut for road reconstruction at STA 14+00 near Evergreen Lane and continued to work on that for the remainder of the week.

Storey Brothers will complete box cut for road reconstruction at the Falmouth Town Line on Thursday, July 26th.  On Friday, July 27th they will place base gravel to prepare for fine grading on Monday, July 30th.  They will be paving the first coarse of binder pavement on Tuesday, July 30th and then begin working on driveway entrance grading and driveway cross culverts.