On Thursday, July 26th Storey Brothers completed the excavation for full depth road reconstruction at the Falmouth Town Line.  The crew began placing and grading reclaim on Friday, July 27th from Evergreen Lane to Falmouth Town Line.  On Monday, July 30th graded the new bus turnaround at 4 Middle Road and fine graded from Evergreen Lane to Falmouth Town Line.  Glidden Paving was on-site Tuesday, July 31st to pave first layer of binder from Evergreen Lane to Falmouth Town Line.    

The crew did not work on Wednesday, August 1st and demobilized from the site.  They will be back at a later date to finish driveway culverts and ditch grading.