Tuttle Road Project - May 26th Update

a

On Thursday, May 17th A.H. Grover completed construction of the block retaining wall in front of 280 Tuttle Road.  On Friday, May 18th the crew installed a 4 inch inserta tee and perimeter drain stub for the proposed addition at 280 Tuttle Road along with working on sidewalk subgrade.  Monday, May 21st the crew performed a live tap and corporation installation along with curb stop for a water service at 280 Tuttle Road. The crew also continued working on sidewalk subgrade from Maurice Way to railroad tracks throughout the week. On Wednesday, May 23rd A.H. Grover assisted PWD with the repair of two air release valves. On Friday, May 25th the crew relocated a hydrant in front of 272 Tuttle Road to make room for the sidewalk.

Work scheduled for the upcoming week will be to continue preparing sidewalk subgrade and setting drainage structure frames and grates/covers. There will be no work on-site Monday, May 28th in observation of Memorial Day.