Tuttle Road Project - July 26th Update

tuttle

On Thursday, July 19th Grover completed removing pavement.  On Friday, July 20th the crew installed the 16 inch ductile iron pipe and fittings near the PWD pump house.  On Monday, July 23rd they began installing 16 inch HDPE water main and completed that work on Wednesday, July 25th

The crew will install hydrant assemblies on Thursday, July 26th and work on water services on Friday, July 27th.  The crew will continue to work on the road reconstruction and on Wednesday, August 1st they will work on cross culvert installation.