Maine Drilling and Blasting continued blasting for water main near Tall Pines Way toward the Falmouth Town Line on Thursday, June 21st and Friday, June 22nd.  On Monday June, 25th Storey Brothers mobilized back on site and began installation of 12 inch water main at Evergreen Lane toward Falmouth Town Line.  Maine Drilling and Blasting finished blasting for water main on Tuesday, June 26th and moved across the road to blast for bus turnaround at 4 Middle Road and for gas main.  Storey Brothers continued installing 12 inch water main and by Wednesday, June 27 were between 15 Middle Road and Tall Pines Way. 

Storey Brothers will complete installation of 12 inch water main on Friday, June 29th.  Maine Drilling and Blasting will continue to work on blasting for gas main.  There will be no work on site for the week of July 2nd.  Storey Brothers will be back on site Monday, July 9th