Middle Road Project - June 6th Update

On Thursday June 7th, Storey Brothers will mobilize on Middle Road and begin placing topsoil, seed, and mulch beginning at the area around 161 Middle Road and continue throughout the project as time permits that day. Storey Brothers will then return to Middle Road on Monday, June 11th and begin blasting bedrock for water main placement just south of Evergreen Lane towards the Falmouth town line. During the week of June 11th Storey Brothers will continue blasting bedrock, site clean-up, and begin water main placement just south of Evergreen Lane.

A representative from Sevee and Maher Engineers will be contacting residents from Evergreen Lane to the Falmouth town line to inquire about a location for their water service shut off towards the end of week ending June 8th and the week of June 11th.