Middle Road Project - June 14th Update

On Thursday, June 7th Storey Brothers mobilized on site to begin clean up at 161 Middle Road and worked their way north.  The crew returned to the site on Monday, June 11th to resume clean-up operations beginning at 100 Middle Road and working their way north throughout the week.  Maine Drilling and Blasting also mobilized onsite Monday, June 11th to begin blasting for bedrock just north of Evergreen Lane and worked toward the Falmouth town line for the remainder of the week. 

On Thursday, June 14th and Friday, June 15th Storey Brothers will finish loam, seed, and mulch to Evergreen Lane where they stop construction last fall.  Maine Drilling and Blasting will continue to blast bedrock for water main toward the Falmouth town line for the remainder of the week.  Storey Brothers will not have a crew on site for the week of June 18th to allow Maine Drilling and Blasting to complete their work.