Birch Lane

s

Storey Brothers Excavation will be onsite on Birch Lane starting Tuesday April 4, 2017 to begin excavation of the lower 200 feet of Birch Lane to allow for the reconstruction of this section of roadway.  As part of the construction, they will be installing approximately 200 feet of 12” storm drain on the North side of the roadway and 2 catch basins at the upper extents of the project limits.   Excavation and drainage installation is expected to last approximately 1 week.  The section of roadway will remain gravel until the paving plants are open.  Pavement will be placed along with sloped curbing along both sides of the reconstruction area.