Tuttle Road Project - May 31st Update

T

On Thursday, May 24th A.H. Grover placed frames and grates on new catch basins and continued subgrade prep on the sidewalk extension from Town Hall to the rail road tracks.  On Friday, May 25th the crew relocated a hydrant at STA 8+75 in front of 272 Tuttle Road.   The crew took Monday, May 28th off to observe Memorial Day and on Tuesday the 29th of May they continued placing frames and grates/covers along with working on sidewalk extension subgrade and new curb pad. 

A.H. Grover left site on Wednesday May 30th and will return the following week on Wednesday, June 6th.  A water main tap in scheduled for Tuesday, June 5th for OceanView at Cumberland which is in the project area and the remainder of the work in that area will be completed by A.H. Grover after the tap is performed.