Tuttle Road Project - June 28th Update

On Thursday, June 21st A.H. Grover installed gate valves for temporary water and water main replacement on the east side of the rail road tracks. On Friday, June 22nd and Monday, June 25th Grover placed and graded gravel to prepare for sidewalk extension paving. Dayton Paving was on site Tuesday June 26th to pave sidewalk base course from rail road tracks to Town Hall.  Grover placed rock in the bottom of the 36 inch culverts in front of 272 Tuttle Road and began clean up on Wednesday, June 27th. Thirsty Turf was also on site to install temporary water line on the east side of the rail road tracks.

Dayton Paving will be back on site Friday, June 29th to pave surface course on the sidewalk extension from the rail road tracks to Town Hall. On Monday, July 2nd and Tuesday, July 3rd Grover will begin clean up (loam, seed, and mulch) from the rail road tracks to Town Hall. Grover will not be onsite July 4th, 5th, and 6th.