Tuttle Road Project - June 25th Update

On Thursday, June 14th A.H. Grover prepped for paved curb pad and additional pavement between town hall and the rail road tracks.  Dayton Paving on-site Friday, June 15th to pave curb pad and cross trenches.  Monday, June 18th Drigo Slipform on-site to install concrete slipform curb from town hall to rail road tracks.  A.H. Grover placed and graded gravel for sidewalk for the remainder of the week. 

A.H. Grover will install two valves on the other side of the rail road tracks to prepare for temporary water.  They will continue placing gravel for sidewalk extension.  A crew will install temporary water at the beginning of the week.  Dayton Paving will be back on site Monday, June 25th to pave sidewalk and A.H. Grover will begin clean up throughout this area.