Tuttle Road Project - July 12th Update

t

A.H. Grover took the remainder of the week after July 4th off. The crew mobilized back on site Tuesday, July 10th to install temporary water services and make connections in work zone area on the east side of the rail road tracks. The crew will take the remainder of the week to fuse water main pipe and prepare for construction on the east side of the rail road tracks. They will begin water main installation on Monday, July 16th and continue with this work the remainder of the week from the rail road tracks to just beyond the Portland Water District Pump Station.