Middle Road Project - July 19th Update

z

On Thursday, July 12th Storey Brothers complete the installation of all water services with 4 Middle Road.  Dave Bernard from PWD on-site to begin filling the new water main.  That afternoon Storey Brothers began the installation of 4 inch underdrain near the existing bus turnaround.  Storey Brothers continue 4 inch underdrain installation on Friday, July 13th.  On Monday, July 16th Storey Brothers began the installation of the 4 inch gas main just south of Evergreen Lane.  They provided the excavation and backfill and Summit gas on-site to install.  They continued 4 inch gas main on Tuesday, July 17th, but left site early due to rain.  Wednesday, July 18th Storey Brothers completed the installation of the 4 inch gas main and underdrain at the Falmouth Town Line.  That afternoon they began removing pavement for full depth road reconstruction. 

From Thursday, July 19th to Wednesday, July 25th Storey Brothers will continue to work on full depth road reconstruction from Evergreen Lane to Falmouth town line.  They will be removing pavement, placing gravel, and fine grading through this area.