Middle Road - Completed News & Announcements

Final Middle Road Paving

The final paving on Middle Road will occur as soon as we have 3 consecutive days without rain. We will post as soon as the paving... more ››

Middle Road Update - November 13th

The final paving of Middle Road will occur in the Spring of 2019. In the next few weeks, crews will be winterizing driveways. This will be... more ››

Middle Road Paving

Paving will begin next week on Middle Road. The work will take approximately 4-5 days to complete.

Middle Road Project Summary

 

w

Middle Road Project - August 2nd Update

On Thursday, July 26th Storey Brothers completed the excavation for full depth road reconstruction at the Falmouth Town Line.  The crew... more ››

m

Middle Road Project - July 26th Update

On Thursday, July 19th Storey Brothers began removing pavement.  On Friday, July 20th they began box cut for road reconstruction at STA 14+... more ››

Middle Road Project - July 19th Update

a

Middle Road Project - July 12th Update

Storey Brothers took the week over July 4th off and mobilized back on site Monday, July 9th.  Storey Brothers began installing water... more ››

Middle Road Project - June 28th Update

Maine Drilling and Blasting continued blasting for water main near Tall Pines Way toward the Falmouth Town Line on Thursday, June 21st and... more ››

Middle Road Project - June 25 Update

On Thursday, June 14th Maine Drilling and Blasting continued blasting bedrock for the water main near 17 Middle Road and Storey Brothers... more ››

Middle Road Project - June 14th Update

On Thursday, June 7th Storey Brothers mobilized on site to begin clean up at 161 Middle Road and worked their way north.  The crew returned... more ››

Middle Road Project - June 6th Update

On Thursday June 7th, Storey Brothers will mobilize on Middle Road and begin placing topsoil, seed, and mulch beginning at the area around... more ››

Middle Road: Construction to Begin Next Week

Construction on Middle Road will resume on Tuesday, May 29th. The work will include blasting for the waterline, loam and seed, and other... more ››

Middle Road Project Update

Daily Report - November 21st

Click on the following link to view the November... more ››

Daily Report - November 20th

Click on the following link to view the November... more ››

Daily Report - November 17th

Click on the following link to view the November... more ››

Weekly Report - November 22nd

Click on the following link to view the ... more ››

Weekly Report - November 15th

Click on the following link to view the ... more ››

Daily Report - November 16th

Click on the following link to view the November... more ››